Data Centres and Nearby Communities

Data Centres and Nearby Communities are becoming an important part of the discussion as South Africa embraces the digital economy. These facilities support online services, digital communications, cloud computing and the growing use of artificial intelligence (AI).
Behind these seemingly invisible services are substantial physical operations requiring land, electricity, cooling systems, water and supporting infrastructure.
The human impact of digital progress
The human implications of these developments become particularly clear at King Air Industria, near Cape Town International Airport. An investigation by Business Day reported that a resident of the nearby Barcelona informal settlement in Gugulethu collects water from a communal tap and uses a communal pit latrine. The settlement is located across the freeway from the proposed data-centre development [1].
This contrast raises an important question: how adequately are the environmental and social consequences of large infrastructure developments being considered, particularly for communities living nearby?
South Africa needs investment and technological progress. The challenge is to ensure that these developments also respect environmental health, human dignity and the wellbeing of neighbouring communities.
When technological progress meets existing inequality
The proposed King Air Industria development highlights the importance of considering the circumstances of neighbouring communities when assessing major infrastructure projects.
King David Golf Club owns the land and has leased it to developers for the King Air Industria project [2].
Nearby communities include Barcelona informal settlement, Bishop Lavis, Gugulethu and Khayelitsha Town Centre (KTC) [3, 4].
Where residents already face difficulties accessing basic services, questions about additional demands on local resources deserve careful consideration. These concerns do not, by themselves, establish what impact a proposed development would have. They do, however, underline why decision-makers should properly understand its potential resource requirements and environmental effects before granting approval.
Planning, information and environmental concerns
The planning and appeal processes have raised questions about anticipated water consumption, electricity requirements, cooling systems, backup generators, emissions and noise.
The developer’s position, as reported by Daily Maverick, is that the current land-use application establishes the planning framework for the development, while more detailed operational matters should be considered at later stages, including the Site Development Plan and building-plan processes. The appellants, represented by the Legal Resources Centre (LRC), have questioned whether deferring these assessments leaves important environmental and resource-related issues unresolved at the point when land-use rights are granted [2, 3, 5, 6].
Public participation and access to information
Meaningful public participation is important. Affected communities need more than access to technical documents. They need a genuine opportunity to understand proposals, raise questions and have their concerns considered.
The King Air Industria appeal: key developments
The proposed development and Equinix’s position
The rezoning application could allow for one, possibly two, data centres at King Air Industria, with a reported electricity-capacity requirement of approximately 174 MVA [4, 5].
Equinix has separately described the King Air Industria site as a “long-term land bank”, saying that it has no immediate plans to develop it and has not submitted any planning or development applications [2]. However, Business Day reported that planning documents identify the two proposed data centres under the King Air Industria application as intended for Equinix [1]. Daily Maverick subsequently reported that Planning Partners was acting on behalf of both King Air Industria and Equinix in the project [6].
The appeal process
The main stages of the appeal process reported publicly were:
- 14 July 2026: The Municipal Planning Tribunal approved the relevant land-use application. The decision was supported by four members, with one member dissenting and raising concerns about the information available on water and electricity requirements [2, 4, 5].
- 6 August 2026: The Housing Assembly and Foxglove lodged a formal appeal, with legal representation from the Legal Resources Centre. The approval was suspended pending the outcome of the appeal [4].
- 12 October 2026: The City’s Planning Appeals Advisory Panel was scheduled to consider the appeal in a closed meeting, which the appellants, members of the public and the media were not permitted to attend [7, 8].
- 5 November 2026: Daily Maverick reported that the appeal-panel proceedings had concluded and that the appellants were awaiting the final decision of the Appeal Authority, identified as the City’s Executive Mayor [6].
The Planning Appeals Advisory Panel and the Appeal Authority have different roles. The Panel considers the appeal and makes a recommendation, while the Executive Mayor is responsible for the final appeal decision. The Panel’s consideration should therefore not be confused with the final determination of the appeal [8].
The appeal is an important part of the planning process. Its outcome, together with the information made available to affected communities, will help determine how the development proceeds and whether their concerns have been adequately considered.
The economic case and environmental responsibilities
There is also an economic dimension to this proposal. Data-centre development can attract substantial investment, support construction activity and specialist employment, and contribute to Cape Town’s ambitions to strengthen its position in the digital economy. These potential benefits deserve consideration. However, project-specific employment figures and the longer-term economic benefits should be clearly established rather than assumed.
Daily Maverick reported that Equinix had paid approximately R33.3 million in Shared Network Charges associated with the development’s infrastructure arrangements. This indicates that significant infrastructure planning and financial arrangements have taken place, but it should not be interpreted as confirmation that construction is imminent or that all aspects of the development have been finalised [6].
Cooling is another important consideration. The developer’s appeal response referred to air-source cooling, which may reduce reliance on water-intensive cooling methods in some circumstances. However, Daily Maverick reported that the LRC questioned inconsistencies in the response about whether the cooling arrangements had been finalised. Air cooling should therefore not be assumed to eliminate water requirements, and the actual demand will depend on the final design and operating arrangements [6].
Existing environmental pressures
The potential impacts of a new development need to be understood in relation to the environmental conditions already present in the area.
The City of Cape Town’s Air Quality Management Plan 2024 identifies residential areas close to Cape Town International Airport as air-pollution hotspot areas. It also identifies household fuel burning, transport and windblown dust from unpaved and exposed areas as contributors to particulate pollution in certain parts of the city, particularly in densely populated, lower-income settlements [9].
These findings do not establish precise pollution levels at the proposed development site or in each neighbouring community. They do, however, highlight the importance of understanding existing environmental pressures. The potential impacts of a major infrastructure project should not be assessed in isolation from the environment in which it is proposed.
Environmental responsibility must apply equally
Environmental responsibility should not depend on a community’s income, influence or ability to challenge a development.
People living in less affluent communities have the same interest in clean air, safe water and a healthy living environment as those living in wealthier areas. Their circumstances should not make their environmental concerns less visible or their health less important.
Environmental health should not be an afterthought
Data centres depend on extensive supporting infrastructure and resources. Their environmental implications therefore need to be considered both at the facility itself and across the wider infrastructure network.
Electricity demand, emissions and air quality
The electricity required to operate data centres can have environmental and health consequences far beyond the facilities themselves. Where additional electricity demand is met by fossil-fuel power stations, associated emissions can contribute to air pollution across wider geographical areas.
A 2026 study by researchers from the Massachusetts Institute of Technology (MIT) and collaborating institutions examined the air-quality and health impacts associated with grid-supplied data-centre electricity demand in the United States. Using models of electricity generation, power-grid connections and atmospheric pollution, the researchers estimated that data-centre electricity demand in 2023 was associated with approximately 650 premature deaths from air pollution across the country. Some of the highest estimated mortality rates occurred in states far from major concentrations of data centres [10, 11].
However, the estimated premature deaths are model-based, not a count of observed deaths directly attributed to data centres. The findings are also specific to the United States and should not be interpreted as a measure of the impact in South Africa. The actual implications elsewhere will depend on the electricity generation mix, grid infrastructure and local environmental conditions.
Water use and local resources
Water demand depends on the cooling technology, the design of the facility and its operational requirements. Establishing the expected consumption is therefore important when assessing the development’s potential demand on local water resources.
Water availability is particularly relevant in the Western Cape. On 16 November 2026, the City of Cape Town announced that Level 1 water restrictions would take effect on 1 December. Residents, visitors and businesses were asked to use at least 10% less water as the region prepares for a longer, hotter and drier summer [12].
Against this background, the water requirements of large new developments, including data centres, deserve careful consideration. The issue is not simply how much water a facility may require, but how that demand fits into the wider needs and priorities of the area.
Backup generators, noise and other on-site impacts
Data centres require reliable electricity supplies, and backup generators may be installed to maintain operations during power interruptions. These generators can produce air pollutants when operated, depending on their fuel, maintenance and operating conditions.
Cooling equipment, fans, transformers and other electrical infrastructure can also contribute to noise. Heat released by equipment and cooling systems may affect the immediate surroundings, depending on the facility’s design and location.
These potential impacts should be assessed using the proposed equipment specifications, expected operating conditions and the proximity of neighbouring homes and other sensitive locations. Appropriate design, maintenance and mitigation measures can help reduce avoidable impacts.
Electromagnetic fields and telecommunications infrastructure
Data centres contain extensive electrical infrastructure, including transformers, power cables, switchgear and power-distribution equipment. These systems generate extremely low-frequency electromagnetic fields (ELF-EMF). The levels present in accessible areas depend on the equipment, electrical load, configuration and distance from the source.
Radiofrequency radiation (RFR) may also be relevant where wireless communications or other radiofrequency equipment is installed. Nearby mobile network base stations may represent additional, separate sources of radiofrequency exposure.
The World Health Organization (WHO) has assessed the scientific evidence concerning exposure to extremely low-frequency fields. Research into the potential health effects of electromagnetic-field exposure continues, and questions remain about some aspects of long-term exposure [13].
An appropriate assessment should identify relevant sources, consider operating conditions and establish exposure levels in areas accessible to workers and members of the public. The existence of electrical or telecommunications infrastructure does not, on its own, establish that exposure levels are harmful. Equally, assumptions about exposure should not replace an assessment where one is warranted.
Possible cumulative environmental exposures
The preceding sections consider several potential impacts separately, including electricity-related air pollution, water demand, generator emissions, noise and electromagnetic fields. Communities living nearby may encounter more than one source of environmental exposure, alongside pressures already present in the area. Assessments should therefore consider the overall exposure context rather than evaluating each source entirely on its own.
Progress should benefit people, not overlook them
South Africa needs investment, digital infrastructure and technological development. But these objectives should be pursued alongside environmental protection and social responsibility.
The Constitution of the Republic of South Africa provides an important foundation for this approach. Section 24 recognises everyone’s right to an environment that is not harmful to their health or wellbeing. It also requires reasonable measures to protect the environment, prevent pollution and ecological degradation, and secure ecologically sustainable development while promoting justifiable economic and social development [14].
The National Environmental Management Act 107 of 1998 (NEMA) reinforces these principles. Its environmental management principles place people and their needs at the forefront, require development to be socially, environmentally and economically sustainable, and recognise the importance of environmental justice and public participation. They also call for a risk-averse and cautious approach that takes account of the limits of current knowledge when decisions may have environmental consequences [15].
The precautionary approach and the prevention or minimisation of environmental harm provide important frameworks for responsible environmental decision-making. For exposure assessment, the ALARA (As Low As Reasonably Achievable) principle offers an additional practical approach to reducing avoidable exposures. These approaches encourage potential risks to be considered, appropriate preventive measures to be taken and research gaps to be recognised. In the context of emerging technologies, this also means improving environmental monitoring.
True progress should improve people’s lives without overlooking the communities that live alongside it.
References
King Air Industria: Planning, development and community concerns
- Comins, L., Saba, A. & Masson, E. (2026). Cape Town’s AI boom could drain a city still haunted by Day Zero. Business Day, 4 September 2026. Read the article.
- van Rooyen, F. (2026). Cape Town to write new rules for big data centre applications. TechCentral, 17 September 2026. Read the article.
- Scott, A. (2026). “We were never consulted” – Cape Town residents challenge Equinix data centre. GroundUp, 28 September 2026. Read the article.
- Bega, S. (2026). Housing group challenges Cape Town approval of Equinix data centre. Mail & Guardian, 21 September 2026. Read the article.
- Broughton, T. (2026). Activists appeal Cape Town data centre approval. GroundUp, 14 September 2026. Read the article.
- Schutters, L. (2026). Cape Town data centre developers say objectors misunderstand the hustle. Daily Maverick, 5 November 2026. Read the article.
- Foxglove. (2026). Local communities and media shut out of Equinix data centre appeal hearing as campaigners call on Mayor to decide before the elections. 9 October 2026. Read the statement.
- Roos, T. (2026). Appeal against Equinix data centre to be heard behind closed doors. Business Day, 11 October 2026. Read the article.
Environmental conditions and resource use
- City of Cape Town. (2024). Air Quality Management Plan 2024. Read the official document.
Data-centre electricity demand and air quality
- Chen, Y., Wang, S., Senga, J.R.L., White, A.S., Wong, A.Y.H., Freese, L.M., Bell, M.L. & Selin, N.E. (2026). Spatially distributed air quality and health impacts of data center electricity demand in the United States. Environmental Research Letters, 21, 214046. https://doi.org/10.1088/1748-9326/aebbd4
- Zewe, A. (2026). Study reveals data centers’ long-distance damage to air quality. MIT News, 19 November 2026. Read the article.
Water use and local resources
- City of Cape Town. (2026). Capetonians called to use 10% less water under Level 1 restrictions this summer. 16 November 2026. Read the announcement.
Electromagnetic fields and exposure research
- World Health Organization (WHO). (2007). Extremely Low Frequency Fields. Environmental Health Criteria Monograph No. 238. Geneva: WHO. Read the official publication.
South African environmental legislation
- Republic of South Africa. (1996). Constitution of the Republic of South Africa, 1996. Section 24: Environment. Read the Constitution.
- Republic of South Africa. (1998). National Environmental Management Act 107 of 1998. Particularly section 2: Environmental management principles. Read the consolidated Act, as amended to 1 April 2025.